Ask the base rate first

The single question that most improves a forecast: how often does this kind of thing usually happen?

01 · The trap

You start with the story

Kahneman and Tversky called this the inside view: you judge a case by its own vivid details and build a plausible narrative. It feels rigorous, but it quietly assumes things go to plan.

02 · The fix

Start with the record

The outside view asks a different question first: what happened to the last hundred cases like this? That historical frequency—the base rate—is your anchor before any story adjusts it.

03 · The evidence

Stories run optimistic

Across 258 major transport projects, nine in ten went over budget, with an average cost overrun of 28%. The inside-view estimates weren't unlucky—they were systematically too rosy.

04 · In practice

It became official policy

The UK Treasury now requires reference-class forecasting: base the estimate on how similar past projects actually turned out, then adjust. Do the same with any headline—anchor on frequency, then move.

Sources: HM Treasury — Supplementary Green Book Guidance: Optimism Bias · Flyvbjerg — What You Should Know About Megaprojects and Why: An Overview (2014) · NFNO Lab methodology